Crews at Lacamas Regional Park kept putting fencing across one closed trail, and someone kept cutting it down. In the end the contractor stopped replacing it and left that trail open. A county project manager described the effort to The Columbian as "a losing battle." The county still asks everyone to stay out of construction areas, whether crews are on site or not.
If you've been walking the lake this fall, you already know about the fences. Both of the big projects at Lacamas this year were scheduled around water. One had to fit a permitted window for work in the creek. The other rides the city's annual lake drawdown. The water-dependent parts got done on schedule. The remaining work depends on an engineering approval for the bridge and on rainfall for the lake, so neither has a firm end date. Through November, the most predictable plan in Camas sits a couple of miles south on NE 4th Ave.
The Bridge Was Two Old Rail Cars
The bridge being replaced carries the main access road in the northeast corner of the park. Walkers and the county's maintenance trucks both use it. According to The Columbian's Oct. 2 report, it was built from two repurposed rail cars that had rusted and corroded. It was still considered safe for pedestrians. The worry was that it could collapse under a work truck. The replacement is a prefabricated steel bridge with a concrete deck. It will be 12 feet wide, down from about 20, and 5 to 10 feet longer on each side of the creek.
Clark County's July 15 announcement said all trails inside the construction area would close, with completion "sometime in November," weather permitting. Crews pulled out the old bridge in August, during the permitted in-water work window, and cleared debris from an old culvert. The county's latest update on the Lacamas Regional Park page, dated Sept. 18, says on-site work will resume once the foundation plans are approved.
That order of work explains why the site has sat quiet for weeks. Evelyn Ives, project manager with the county's parks and lands division, told The Columbian that the contractor has been working through submittals, the requests for materials and equipment that come with any construction job:
"In a normal situation, we probably would have just delayed the start date. Because of our environmental permits, we had to do the removal and the demo and the in-water work … in the work window."
So demolition went first because the creek required it, and the rest is following at the pace of the paperwork. The Columbian reported that the bridge, first expected by Nov. 15, will now likely be finished in late November or early December. The project is running about $70,000 under budget. Nutter Corp. won the contract with a $485,000 bid, against an engineering estimate of $811,000. Ives also told the paper that the bridge is such a critical piece of the trail that no safe detour exists.
The Lake Runs on a Different Clock
The second project belongs to the City of Camas, which owns and runs the Round Lake dam. Every year the city draws down Lacamas Lake and Round Lake so the dam can be inspected and repaired. This year's drawdown started at 8 a.m. on Monday, Sept. 21. The plan lowers the lakes by about six feet and expected the low point around Oct. 5. The city is also replacing parts of the dam this year, and its notice says that's why the work needs more time than usual.
The end of this project depends on rain. After inspections and repairs are done, the city's drawdown notice says refilling the lakes should take "several weeks, depending on rainfall volumes." Expect lower water and wider exposed shoreline than you're used to for at least part of November.
Trail access near the dam has shifted since summer. In July, the county said trails around the dam would stay open, with flaggers stopping walkers while equipment moved. The city's later notice warns of "significant trail closures around Round Lake" and asks visitors to follow closure signs. The county's closure map marks a small area on the southwest side of Round Lake, near the dam, as closed from 9/15 to 11/15. When the signs on the ground disagree with an older announcement, go by the signs.
| Project | Run by | Map label | Latest word |
|---|---|---|---|
| Northeast bridge replacement | Clark County Public Works, with contractor Nutter Corp. | Trails closed 8/1 to 11/15 | Finish likely late November or early December, per The Columbian's Oct. 2 report |
| Round Lake dam maintenance and lake drawdown | City of Camas Public Works | Trails closed 9/15 to 11/15 | Refill takes several weeks after repairs, depending on rainfall |
Where the Walk Still Goes
The county map carries its own warning: "Map for reference only. Unmarked trails exist. Use at your own risk." The two closure zones sit at opposite ends of the park. One is the northeast corner around the access bridge. The other is the small area by the dam. Lacamas Regional Park, at 3344 NE Everett St., is still open 7 a.m. to dusk, which the county defines as half an hour after sunset. In November, dusk comes early.
On the south shore, the city describes the Heritage Park trail along Lacamas Lake as accessible year-round. Clark County calls the Heritage Trail the south-shore connection. Neither page is a live report on conditions, so check the posted signs at the trailhead. If you cross through the park by bike, expect to be stopped by the bridge site. One park user told The Columbian that the construction "bisects the park."
Downtown's Calendar Covers the Same Weeks
The Downtown Camas Association has something on almost every week between now and the bridge's new likely finish. The dates are fixed, nothing depends on a review or the rain, and most of it is a short walk from the Camas Library.
- Friday, Nov. 6, 5 to 8 p.m. The First Friday theme is "Thankful for YOU! (and pie)," a multicultural celebration. Start at the DCA tables in the Fuel Medical lobby, 314 NE Birch St., where Lore Tea + Coffee is donating pie tastings and you can drop off unwrapped toys for Toys for Tots. Evergreen Vinyl cuts the ribbon on its expansion at 321 NE 4th Ave. at 6 p.m. The Pie Walk Dance Party starts at 7:30 p.m. at 304 NE 4th Ave. Art receptions run at Attic Gallery, 419 NE Cedar; Gallery 408, 408 NE 4th; RedDoor Gallery, 411 NE Dallas; and Second Story Gallery, upstairs at the Camas Library, 625 NE 4th Ave.
- Thursday, Nov. 12, 4 to 9 p.m. At the Holiday Sip & Shop, check in at Fuel Medical Group. A $25 ticket gets you a passport of tasting locations and one entry for an "Explore Downtown Camas" package that includes movie tickets at the historic Liberty Theatre. Each $10 you spend downtown that evening earns another entry. The event raises money for the Downtown Camas Association, and a second date follows on Dec. 10.
- Friday, Nov. 27, 10 a.m. to 6 p.m. For Little Box Friday, participating shops post QR codes inside their stores. Scan one to see that shop's special. The DCA says more shops are still being added.
- Saturday, Nov. 28, 10 a.m. to 5 p.m. On Small Business Saturday, purchases at participating shops come with a Golden Ticket, and each one is a chance at $1,000 in Camas Cash. DCA elves will hand out chocolate bars sponsored by Sweet Intention Gift Boutique, some hiding $50 Camas Cash tickets.
- Friday, Dec. 4, 5 to 8 p.m. Hometown Holidays is organized by Camas Parks & Recreation. The tree lights at 5 p.m., followed by falling "snow," photos with Santa, free hot cocoa, choirs and street food vendors.
The tree lighting on Dec. 4 lands right in the late-November-to-early-December window The Columbian gave for the bridge. Downtown's busiest stretch and the end of the Lacamas closures may arrive within days of each other.
Two New Stops Between Events
Radiate Coffee and Community recently opened on the west end of Camas. The menu includes house-made cinnamon rolls and New Zealand-style ice cream. The Post-Record describes it as a gathering place for the community and for people of all abilities. Downtown, a new Little Wings Library lending box had its ribbon cutting Oct. 2. It's a nonprofit book-access project founded by Camas resident Laura Sheppard, and Discovery High School students built the box.
When the new bridge opens and the lake fills back up, I'll be curious to see which loop people go back to first. If you're weighing a move around Lacamas or downtown and want to know how projects like these show up in nearby home values, Karen Higgins offers a free home valuation and local market consultation. I'm happy to walk through what's changing on your street.